Natomas Levee Improvement Project PDF Print E-mail
Wednesday, 04 November 2009 00:00

Location:
Entire perimeter levee system including the Sacramento River, American River, Natomas Cross Canal, Pleasant Grove Creek Canal and Natomas East Main Drain Canal

Description:
The Natomas Levee Improvement Project is currently under construction by the Sacramento Area Flood Control Agency (SAFCA).  The most current information on this project is available at their website www.safca.org.  This $600 million project which began in 2007 will provide Natomas with 200 year flood protection upon completion. The project primarily addresses the significant underseepage risk which threatens the stability of the levee during high river stages.  The project will include improvements to the entire perimeter levee system surrounding Natomas and include a new “adjacent levee” for the full length of the Sacramento River along the Garden Highway.  Other project features include slurry walls, landside berms and relief wells.  The project also includes environmental enhancements such as woodland corridors, wetlands, and canals to offset the impacts of the project.

Schedule:
Construction began in 2007 and will continue until at least 2014.  For more specific information on projects under construction during the current year, visit the SAFCA website at www.safca.org

Contact:
Questions about the planning, design and engineering aspects should be directed to SAFCA’s project manager John Bassett at 916-874-7606 or This e-mail address is being protected from spambots. You need JavaScript enabled to view it

Issues during construction should be directed to SAFCA’s designated ombudsman Jay Davis at 916-350-0600 or This e-mail address is being protected from spambots. You need JavaScript enabled to view it

Last Updated on Thursday, 05 November 2009 15:54
 
Sacramento River Bank Protection Project RM 73.5L PDF Print E-mail
Tuesday, 03 November 2009 00:00

Location:
Along the Sacramento River about a half mile south of Elverta Road

Description:
This project is being done by the Army Corps of Engineers and involves the placement of large rock along the river’s edge to stop the continued erosion of the bank which is now threatening to erode the adjacent levee.  The rock will be delivered to the site by large trucks traveling along the Garden Highway to the site.  Plants and other woody vegetation will be interspersed in the rocks to provide habitat  

Schedule:
Construction began October 12 and is anticipated to last until early December

Contact:
Questions or concerns should be directed to the Army Corps of Engineers Project Manager Allison Stucky at This e-mail address is being protected from spambots. You need JavaScript enabled to view it

Last Updated on Thursday, 05 November 2009 15:54
 
Sacramento River site R1 PDF Print E-mail
Monday, 02 November 2009 00:00

Location:
Garden Highway between Gateway Oaks and Orchard Lane in front of the District Office at 1633 Garden Highway

Description:
T
he project is being constructed by the Army Corps of Engineers and involves placement of a slurry wall approximately 70 feet deep in front of the District’s office.  Upon completion, the slurry wall will prevent underseepage  in this vicinity and stabilize the existing levee.  Construction will require complete closure of Garden Highway for several days and the partial closure (one lane traffic) for up to six weeks.

Schedule:
Construction began October 12 and is anticipated to be completed in early December

Contact:
Questions or concerns should be directed to the Army Corp of Engineers Project Manager John Hoge at This e-mail address is being protected from spambots. You need JavaScript enabled to view it

Last Updated on Thursday, 05 November 2009 15:54
 

Reclamation District No. 1000
1633 Garden Highway, Sacramento, CA 95833-9706
Tel:(916) 922-1449 Fax:(916) 922-2129


© 2009 Hosted and designed by c.Spot InterWorks